Article in Building Magazine, 22 February 2002
Smooth Operator
by Tony Blacker
The SCL protocol on extensions of time, which is still in draft
form, is provoking a great deal of discussion. Although the JCT
contracts attach little importance to the document, the NEC describes
at great length what the contract programme has to contain.
Both the NEC and the traditional ICE contracts set up machinery
designed to produce both an agreed contract programme at the outset
and a procedure for updating it regularly. But there can be no guarantee
that agreement will be reached on an acceptable programme even at
the beginning of the project, let alone updated programmes, as the
work proceeds, unless, of course, it is identified in the contract
itself before it is signed. But if the document has no contractual
status, what is all the fuss about?
The answer, surely, is that a contract programme is a vital management
tool for contractor and contract administrator (CA). A realistic
programme submitted at the outset, agreed by the CA and updated
at monthly intervals (and following any award of an extension of
time) so it reflects actual progress and a realistic forecast of
future events will make a major contribution to the smooth running
of a project.
The protocol produces model clauses along these lines. Among other
things, it recommends that when contractors make applications for
extensions of time, they should submit a sub-network for insertion
into the updated contract programme showing the expected effect
of any delaying event that might entitle them to an extension. The
intention is that, wherever possible, the parties should agree the
impact of such events as the work proceeds.
But how should the contract provide for the everyday situation
where such agreement cannot be reached? The protocol recommends
that the view of the CA should prevail unless and until overturned
under the relevant dispute resolution provisions of the contract.
What this suggests is that if a contractor provides an updated programme
that is considered unrealistic, the CA may amend the programme.
The revised programme can then be used as the baseline for assessing
extensions of time and for running the contract generally. And if
the contractor is unhappy, he should invoke adjudication.
If a difference of view emerges about whether or not an updated
programme is realistic, or about entitlement to an extension of
time, should an aggrieved contractor be encouraged to start adjudication
proceedings?
Adjudication is, by its nature, confrontational. Would it not be
preferable for the parties to be encouraged to use some form of
mediation? Contracted mediation, for example. Somebody well respected
who knows the project might work wonders, whereas an adjudicator
could wreak havoc.
What then about sanctions generally for breach of programming obligations?
If a contractor on the NEC contract fails to produce a first programme
(but not a subsequent one) he may be subject to a compulsory retention
of up to one-quarter of the price due to him for work done. The
protocol endorses this approach in its model clauses, offering as
an alternative a clause providing for liquidated damages to be payable
in the event of failure to produce an original or updated programme.
Liquidated damages would seem to be the better solution. They could
be calculated on the basis of the expected cost to the employer
of doing what the contractor failed to do. The third optional sanction
offered by the protocol, namely, that such a breach should be deemed
an "event of default" triggering termination rights, seems
a little draconian.
And what about sanctions on the other side of the equation? If
the CA or engineer fails to respond to a programme submitted by
the contractor should he be "deemed" to have accepted
it? That sanction is contained within the ICE conditions and will
be thought appropriate by contractors infuriated with endless delays
by the client's man. On the other hand, to deem an unrealistic programme
to be the benchmark by which a project should be judged will produce
its own problems.
The programme is not, at least in a traditional contract, a document
laying down legal obligations. It should be regarded as a guide
to a CA, but should not be regarded as cast in stone.
The protocol contains much for which we should be grateful, but
its tackling of sanctions for programming defaults is perhaps not
the last word on the subject.
Tony Blackler is a partner in solicitor Macfarlanes.
Reproduced with permission from Building Magazine
(http://www.building.co.uk)
|