Article in Building Magazine, 5 July 2002
Just cool it
A draft delay protocol is supposed to take the heat out of
the contentious area of delay. But as it stands, it could simply
makes things worse
By Nick Henchie
The Society of Construction Law's protocol for determining extensions
of time and compensation for delay and disruption has been downloaded,
discussed, debated and written about for a number of months. Already
a second draft has been produced, and the consultation process continues.
We can expect further amendments in due course. No consensus it
seems can be reached on anything in the protocol, least of all what
its purpose is.
Although there can be no doubting the interest the protocol has
generated on the issue of delay and programming, many people contend
that it has achieved little else. It purports to provide the materials
necessary for parties to avoid unnecessary disputes, but I suspect
that in practice, where adopted by the parties, the protocol is
more likely to lead to an increase in disputes and higher construction
costs.
The protocol suffers from the fact that the drafters appear not
to have considered whether what they have proposed as best practice,
would, if adopted, assist in avoiding disputes on construction projects.
The essence of the protocol is that detailed programming throughout
the life of a construction project will enable delaying events,
be they the responsibility of the employer or the contractor, to
be accurately assessed and managed during the course of the project.
Of course, such a proposal is put forward without the protocol having
been tested on a single construction project, so its success or
otherwise is necessarily hypothetical.
Among the solutions proposed by the protocol, and regarded by the
drafters as best practice, is for the impact of every individual
variation on a project to be plotted on to the programme using modern
project-planning software to show the particular effects of each
single variation on the programme. For a project of any size and
complexity, the time and cost involved in carrying out such an analysis
would be out of all proportion to any possible benefits that could
be obtained. Even on straightforward contracts, variations quite
often number many thousand.
Gauging the impact of all of these individually even when
there is no dispute as to delay is an unnecessary burden
to the contractor.
To then have to agree the impact with the employer, failing which
the employer's decision stands (until overturned in adjudication)
is a recipe for disputes. The further one gets down the contractual
chain, the more ludicrous the recommendations of the protocol become.
Furthermore, it is naïve in the extreme to think that by addressing
the factors that cause delay on projects, during the life of the
project, the parties are more likely to resolve their differences.
Issues of delay are often as contentious during the course of a
project as they are at the end, and sometimes more so. There is
no evidence to suggest that adopting the protocol will reduce the
chance of disputes. Often parties take commercial views on delays
at the final account stage and wrap them up on a commercial basis.
They are not able to take such a view during the infancy of a major
project. The protocol takes no account of the fact that most construction
projects do not end with disputes over delay and are not programmed
with even a fraction of the detail and cost that the protocol recommends.
Everyone knows that proper programming, if not quite a prerequisite
to a successful project, is at least a key factor. There is no doubt
that parties to construction contracts should spend more time planning
how a project is going to be constructed. However, they do not need
the SCL to advise them of this, especially when no analysis of the
likely cost of adopting their recommendations has been carried out.
It will be interesting to see how many employers are willing to
pay contractors to programme a project in such a way and
even more interesting to see if this avoids, or simply creates,
further disputes. Perhaps this sort of analysis should have been
carried out before such proposals were put forward as best practice.
Nick Henchie is a senior solicitor in the Construction &
Engineering Group at Mayer Brown Rowe & Maw and can be contacted
at nick.henchie@eu.mayerbrownrowe.com
Reproduced with permission from Building Magazine
(http://www.building.co.uk)
|