Article in Building Magazine, 19 July 2002
Third time lucky?
by Melinda Parisotti
Nick Henchie (5 July, pages 46-47) left no doubt as to his views
on the Society of Construction Law's protocol for determining extensions
of time and compensation for delay and disruption. But, apart from
its less than catchy title, is it really the antithesis of all that
is good and worthy in the construction world?
Although Henchie makes some valid points, I am less inclined to
condemn the protocol entirely. It contains a good deal of valuable
advice, and the second draft is a notable improvement on the first.
Nevertheless, it still has a long way to go. What are the main changes
in the second draft and what further amendments are necessary?
The status of the document still evades all attempts to be pinned
down precisely. We are no longer presented with a choice of two
confusingly similar alternatives, both of which seemed roughly to
amount to the protocol being used to deal with issues the building
contract is unclear of. However, just as that particular fog is
lifted, the second draft advises, at one point, against incorporating
the entire protocol into the contract, and elsewhere advises against
incorporating only part. And, despite the provision that the building
contract takes precedence over the protocol in the event of conflict,
the fact that the protocol introduces terms contradictory to those
of standard-form contracts will inevitably cause confusion and increase
claims. Surely for this reason, and to address the criticism that
the protocol is overly prescriptive, it should be no more than a
guide without contractual status. At the very least, it should indicate
at the end of each section exactly how it conflicts with each of
the standard forms.
"To address the criticism that the protocol is overly prescriptive,
it should have no contractual status"
The provision that the float be used on a "first come, first
served" basis in terms of employer or contractor delay caused
gnashing of teeth among contractors, who tend to regard the float
as their own personal lifeboat. The second draft addresses this
to some extent, allowing the contractor to preserve some time exclusively
for its own delay.
This new draft no longer requires that the contract administrator
(CA) "approves" the programme, but instead that they "accept"
it. This should take some of the heat off the CA, but acceptance
still amounts to an acknowledgement that the programme is achievable,
presumably making the CA partly responsible for it. This cannot
be right. The programme is intrinsically linked to price. Both are
contractor-controlled and both should be matters exclusively for
contractor risk.
The first draft of the protocol seemed to invite parties to bolt
straight off to adjudication in the event of any dispute over what
constitutes the "accepted programme" rather perplexing
in a document which complained that delay issues "all too often
become disputes which have to be decided by third parties".
Thankfully, sanity has now prevailed and adjudication is no longer
promoted as a knee-jerk reaction.
As a sop to complaints that the protocol is too prescriptive and
unduly ties the CA's hands, the SCL has now emphasised the need
for the CA to apply common sense and experience. However, I doubt
this will prove sufficient to prevent inexperienced CAs playing
safe by following the protocol in preference to their own initiative.
Most disappointingly, this second draft has done nothing to address
the valid concern, expressed by Henchie and others, that the protocol
places too great an administrative burden on the parties in terms
of programming and record-keeping, which will inevitably increase
construction costs.
The publication of the delay protocol will, ironically, be delayed
until later this summer. The SCL has advised that it is being "refined"
to take account of feedback received. "Refinement" sounds
disturbingly conservative in view of the radical changes necessary.
The protocol is a potentially useful guide with immense significance.
If the SCL doesn't want egg on its face, it needs to get it right.
(Melinda Parisotti is an in-house barrister at Wren Managers, which
manages a professional indemnity mutual for architects.)
Reproduced with permission from Building Magazine
(http://www.building.co.uk)
|