Article in Building Magazine, 1 November 2002
A landmark protocol....
by Tony Bingham
read this article as a PDF
The Society of Construction Law has just launched its Delay and
Disruption Protocol. It's a splendid guide to solving extension
of time and compensation problems
Go to www.eotprotocol.com please. Download the Delay & Disruption
Protocol; it's yours free. Two years of work and one year of consultation
have gone into this splendid work. It is the first major policy
document in the Society of Construction Law's development. And it's
a landmark. The only mistake is to call it a protocol. In truth,
it is just a guide. Oh, it's a very good guide for managing change
on a construction project, change that threatens the programme and
the completion date and claims for lateness. The aim is that, in
time, most contract documents will adopt this "guide",
as the best way to deal with delay and disruption issues. The trouble
with that remark is that it carries the implication that what lurks
in the plethora of standard forms right now is not quite ticketyboo;
that the protocol is a better bet. Ruffled feathers, eh? But, believe
me, what the industry really cries out for is one set of clear rules
for managing change on a project. Clear enough to be understood
by builders, rather than lawyers.
So, what does the "guide" guide us to? First, it demands
not just a building programme showing manner and sequence, it demands
a record of actual progress. This is the tool for managing change.
The benefit for the employer is to establish a revised, later date
from which damages will run.
Then the idea is to deal with extensions of time soon after the
delay event. A shift of thinking is needed here. The employer is
inclined to want to wait to see what the effect of a delay event
really is. The contractor, in this guide, will be entitled to require
the architect/engineer/contract administrator to predict the effect
of the event and add time immediately. Then any later knock-on delays
that are traceable back to the root event will be given more time.
Float at the back end of the programme is tackled head on. It is
daft to have a programme that hasn't got an actual finish at least
a few weeks before the formal contract completion date. If a delay
occurs that eats into that float and that delay would ordinarily
extend time, the protocol says no to an extension; but it says yes
to compensation because the contractor's work has been disrupted.
A lot of current contract documents would suggest an extension of
time is appropriate, but there is an air of reality about the protocol's
stance.
There will be arguments about all this. Concurrent delays –
that is, delay events warranting a time extension that occur simultaneously
– entitle the contractor to an extension of time. But the
extension may not therefore carry money compensation since the contractor
has suffered no loss. So, there you are ready to put the roof on
today but the architect has indicated a change to the wall plate
design. The job stops. True, the builder can do bits and bobs here
and there but what's the predicted effect? Whatever it is, he gets
an extension of time now. And if later because of the roof delay
a subcontractor can't get back as and when wanted and that delays
the job some more, another extension is given.
Then what of mitigation? The protocol makes plain that mitigation
does not extend to requiring the contractor to add extra resources
or work outside planned working hours. And what of financial consequence
of delay? The reminder is that extensions of time are often neutral
events for which neither builder nor employer pays. They are best
thought of quite separately from money. Those events that do have
financial consequences, however, are costed to a system. Come to
think of it, the effect can be pre-priced. Interest, global claims,
overheads, disruption, acceleration are all here, even a guide to
software.
The Society of Construction Law is a neutral body heaving with
ordinary members each of whom know the reality of building and civil
engineering. It is dedicated to providing a transparent and unified
approach to the everyday events in the real world. For my money
I don't actually care very much what the rules are, so long as they
fairly allocate risk and above all can be understood by ordinary
building folk. Have a look at all this, please. The idea is to simplify
and make user-friendly. It might even make buildings better.
(Tony Bingham is a barrister and arbitrator specialising in construction.
You can write to him at 3 Paper Buildings, Temple, London EC4 7EY,
or email him on info@tonybingham.co.uk)
Reproduced with permission from Building Magazine
(http://www.building.co.uk)
|