Article in Building Magazine, 1 November 2002
....but fundamentally flawed
by John Sims
read this article as a PDF
Admirable in some ways, the protocol has it got it badly wrong
in the advice it gives on the subject of float as it relates to
extensions of time
The Delay and Disruption Protocol is an admirable document in many
ways. But in one important area it is in my view, fundamentally
wrong in the advice it gives, and that is in the treatment of programme
"float" in relation to extensions of time.
Paragraph 1.3.1 states that where there is remaining float in the
programme, an extension of time should only be granted if the employer
delay is predicted to reduce this float below zero, thereby actually
extending the works beyond the formal contract completion date.
This is completely to misunderstand the primary purpose of an extension
of time, which is to preserve the employer's right to liquidated
damages by fixing a new, later date by which the contractor is obliged
to complete the works if the progress of the work is delayed by
the employer or its contract administrator. It has nothing to do
with the contractor's intentions as to completion. Whatever float
the contractor has built into its programme to allow for unforeseen
events for which no extension will be granted, should still be available
to it.
The fallacy of the protocol's approach is vividly illustrated by
paragraph 1.3.4, which contains two propositions which I read with
disbelief. The first is that if an employer delay occurs first and
uses up all the float, then "the contractor can find itself
in delay and paying liquidated damages" as a result of any
subsequent contractor delay that would not have been critical had
the employer delay not occurred first. All I can say is that, if
an employer were foolish enough to deduct damages in such circumstances,
it would rapidly find itself in court being ordered to pay them
back. Any contract administrator who advised it that it should do
so would be guilty of professional negligence.
The second proposition is this: "Under contracts where the
employer delay only has to affect the contractor's planned completion
date, the contractor is potentially entitled to an extension of
time every time the employer … delays any of its activities,
irrespective of their criticality to meeting the contract completion
date."
In more than 50 years' in the building industry, I have never come
across any contract that expressly links delay and extensions of
time to "the contractor's planned completion date". To
do so would effectively be to make that the contract completion
date, which is an obvious nonsense.
Obviously, any contract administrator considering the grant of
an extension of time must consider whether the delaying event affects
any activity critical to completion of the work. If it does not,
no extension should be granted. If it does, even though the contractor's
programme suggests that it will still complete before the contract
completion date, an appropriate extension should be granted to preserve
the employer's right to damages if, in the event, the remaining
float is used up due to other delays.
One of the problems is that clause 25.3.1.2 of JCT80 requires the
contract administrator, on receiving notice of a delay, to grant
an extension if "the completion of the works is likely to be
delayed thereby beyond the completion date". Those last four
words appear to suggest that the administrator should only grant
an extension if the delaying event will, in fact, delay completion
beyond the contract completion date. In my view, those words are
redundant and misleading.
The only remedy is for the JCT to take immediate steps to delete
the four offending words from future editions of all their contracts,
and for the drafters of the protocol to change paragraph 1.3 in
the interests of preserving employers' rights to levy damages without
exposing themselves to legitimate challenge.
(John Sims is a consultant, arbitrator, adjudicator and mediator
in construction disputes.)
Reproduced with permission from Building Magazine
(http://www.building.co.uk)
|