Article in Building magazine, 11 January 2002
GETTING IN EARLY
by Tony Bingham
The Society of Construction Law has brought out a
best practice guide for those gearing up for a dispute about
delay. Do yourself a favour and download it now
Now then, here is an interesting contribution.
It is described as "material necessary for parties to avoid
unnecessary disputes". And, given our infinite capacity for
differences of opinion, any straw in the wind is welcome.
The "unnecessary disputes" concern "time". That
gets us into extensions of time, liquidated damages, concurrent
delays and who owns "float". Then it gets us into disruption and
global claims, and then, oh then, it gets into "collapsed as
built", "but for …", "lag finish to finish", "start to start",
"negative lag programmes". You understand that kind of jargon, of
course, but some folk are flummoxed.
So, a group of sound people sat down under the
umbrella of the Society of Construction Law and had a think. This
group, led by top construction lawyer Jeremy Winter, of Baker &
McKenzie, has produced a 70-page guidance note called A
Protocol for Determining Extensions of Time and Compensation for
Delay and Disruption (you can download the draft form free –
go to www.eotprotocol.com).
I reckon it will have a major effect on this sometimes difficult
area of construction.
What is the protocol for? Well, you could
include it as a contract document since it explains things such as
float and ownership of concurrency. It would also help to explain
the meaning of words and phrases to do with programming in the
contract. More likely, though, the protocol will be used to beat
the other chap over the head when he doesn't agree with your point
of view.
That's not a throwaway remark; the truth is
that the people who made up the drafting committee and the people
who added bits here and there are a strong representation of the
building dispute management business. All told, 50 people
contributed. That's a lot of expertise to beat up the other bloke
with. Mind you, I don't actually agree with all of it, as I'll
explain in a moment.
Hurrah, though, for a start, for the protocol's
dictionary. It is seriously good stuff. I honestly didn't know
what "activity-on-the-node" was before the protocol enlightened
me. At last, there is a definition of "constructive acceleration",
"a hammock", "a Gantt chart", and more besides.
Hurrah, too, for switching the talk of "time"
from disputes territory to the reality that delay and disruption
are for ordinary management to sort out, just as much as
delivering paving slabs. The protocol simply explains how a
transparent and unified approach to programming through proper
recording and identifying the consequences of delay and
disruption, is everyday "managing". And if you don't know about
"time-input" analysis, here is your chance to learn.
As to the programme itself, the protocol
inevitably teaches grandmother to suck eggs. But damn it, there
may be some folks out there who still don't use the most basic
software for critical path networks. And, come on, it doesn't need
a protocol to coax you to use software to predict the effect of
change. I mean, this is everyday stuff – I think. And here it
gives a code for combining the programme with the method
statement. People in an adjudication will fall about laughing if
you haven't submitted draft programmes at the right time, or
haven't adopted a mechanism for archiving the weekly updates.
As for extensions of time, the guidance at last
explains that these are nothing to do with loss and expense
claims, or rather, they're best thought of separately. It states,
accurately, that: "Where a contractor delay to completion occurs
concurrently with employer delay to completion, the contractor's
concurrent delay should not reduce any extension of time due."
And as for money, it even explains that the
awarding of extensions of time for concurrent delay does not
automatically run up a prolongation claim.
There is good stuff on head office overheads,
claiming of quite separate stuff called profit. I like the note
about claim preparation costs, which I hope some adjudicators will
think about.
Where I disagree with the 50 experts, is on
their throwaway approach to a global claim. The protocol condemns
these contractor claims. They want each bit of disruption to be
linked to resultant loss.
Tosh. Come on, chaps, get back on site. Global
claims deserve much more detailed analysis of the recent cases. It
is unwise to say they don't stack up. They do … sometimes.
The protocol is aiming to help provide common
ground. Get it, and contribute to it – you've got until
31 January. Tell the Society of Construction Law where you think
it's adrift.
Taken with permission from Tony Bingham's website: http://www.tonybingham.co.uk
Building magazine can be found at
http://www.building.co.uk/
|