Article in Construction Industry Law Letter, January 2002
Protocol for Determining Extensions of Time and Compensation for
Delay and Disruption
On 4 December 2001 the Society of Construction Law issued in draft
a new protocol to act as a guide on how to record and manage delay
in the construction process. The protocol is intended to limit the
scope for argument about causes of delay and provides detailed guidance
for the efficient resolution of disputes on projects where there
has already been delay. The protocol runs to some 68 pages and was
drafted by a panel of experts from all sections of the construction
industry. A summary of the main points in the protocol is included
here but the text of the protocol in full is available on a special
Society for Construction Law website at www.eotprotocol.com. The
Introduction to the Protocol states that its purpose is to provide
the material necessary for the parties to avoid unnecessary disputes.
If the parties to a contract agree, whether at the time of entering
into the contract or later, the Protocol can be used as an aid to
deciding issues that are not clearly covered by the contract. This
might include matters such as the ownership of float and concurrency.
If the parties have agreed that the Protocol should be used as
an aid to interpretation of their contract, the Protocol will prevail
over any conflicting case law, but where the Protocol conflicts
with any term of the contract, the contract term shall take precedence.
The Protocol envisages that even where the contracting parties
have not adopted the Protocol, decision-takers (eg contract administrators,
adjudicators, dispute review boards, arbitrators, judges etc) may
still find it helpful in dealing with delay issues, in much the
same way that they might look at a textbook.To the extent that they
are not bound by judicial precedent, decision-takers may prefer
to follow the guidance in the Protocol to case law that conflicts
with it.
The Protocol contains guidance as to matters which should be addressed
when the contract is being drafted and negotiated in order to improve
upon the way that standard forms of contract generally deal with
delay issues. The protocol, which is currently in draft form, will
be subject to a public consultation, until 31 January 2002. The
finalised protocol is to be published in April 2002. An extract
of the section of the protocol headed 'Summary of main points in
the Protocol' is set out below.
* Programme - The contractor should submit and the contract administrator
should approve a programme (using industry standard critical path
method project planning software) showing the manner and sequence
in which the contractor plans to carry out the works and identifying
where the critical paths lie.
* The Protocol recommends that a provisional sum be allowed by
the Employer in the contract price for the provision by the contractor
of a proper programme, and further payments for properly updating
the programme.
* Purpose of extension of time - An extension of time (EOT) serves
only to relieve the contractor of liability for liquidated damages
for any period prior to the extended contract completion date.
* Entitlement to EOT - Applications for EOT should be made and
dealt with as close in time as possible to the delay event that
gives rise to the application.The contractor will be potentially
entitled to an EOT only for Employer Delay arising from Employer
Risk Events - being those causes of delay in respect of which the
Employer has assumed risk and responsibility. Correspondingly the
Protocol uses the terms Contractor Risk Event and Contractor Delay.
* Procedure for granting EOT - The Updated Programme (being the
approved programme brought fully up to date to the point immediately
before the occurrence of the relevant Employer Risk Event) should
be the primary tool for determining the amount of the EOT.The EOT
should be granted to the extent that the Employer Risk Event is
predicted to prevent the works being completed by the then prevailing
contract date for completion.
* Float as it relates to time - An EOT should only be granted to
the extent that the Employer Delay is predicted at the time of the
Employer Risk Event to reduce below zero (or, if already in delay,
to further reduce below zero) the total float on the activity paths
affected by the Employer Delay viz. only to the extent that the
activity paths are (or are anticipated to be) critical to completion
on the then prevailing contract completion date, at the time the
Employer Risk Event occurs.
* Float as it relates to compensation - If, as a result of Employer
Delay to Progress, the contractor is prevented from completing the
works before the contract completion date, the contractor should
in principle be entitled to be paid the costs directly caused by
the Employer Delay to Progress, notwithstanding that there is no
delay to the contract completion date (and therefore no entitlement
to an EOT), provided also that such costs were in the contemplation
of the parties when they entered into the contract.
* Concurrent delay - its effect on entitlement to EOT - Where Contractor
Delay to Completion occurs concurrently with Employer Delay to Completion,
the contractor's concurrent delay should not reduce any EOT due.
* Concurrent delay - its effect on entitlement to compensation
for prolongation - If the contractor incurs additional costs that
are caused by both Employer Delay and Contractor Delay, then the
contractor should only recover compensation if it is able to separate
the additional costs caused by the Employer Delay from those caused
by the Contractor Delay.
* Mitigation - The contractor has a general duty to mitigate the
effect on its works of Employer Risk Events.The duty to mitigate
Employer Delays, however, does not extend to requiring the contractor
to add extra resources or to work outside its planned working hours
in order to reduce the effect of an Employer Risk Event, unless
the employer agrees to compensate the contractor for the costs of
such mitigation efforts.
* Delay analysis - The Protocol recommends that 'time impact analysis'
should be used, as a delay analysis methodology, wherever possible,
both for prospective and retrospective analysis.Time impact analysis
utilises a critical path network of the works, that is updated periodically
(usually each month) and when any Employer Risk Event occurs (eg
any employer liability variation, delayed instruction, or a claim
event such as lack of access) or contractor delays. Each of these
updated networks is saved electronically. The analysis therefore
records a moving simulation of the construction of the works. In
respect of retrospective delay analysis, the Protocol recommends
that the method of analysis should be agreed between the parties
before either party begins the analysis.
* Link between EOT and compensation - Entitlement to an EOT does
not automatically lead to entitlement to compensation.
* Pre-agreeing full effect of variations - The Protocol supports
the practice of pre-agreeing where practicable the total likely
effect of variations, to arrive at, if possible, a fixed price of
a variation, to include not only the direct costs (labour, plant
and materials) but also time-related costs.
* Basis of calculation of compensation for prolongation - Unless
expressly provided for otherwise, compensation for prolongation
should not be paid for anything else other than work actually done,
time actually taken up or loss and/or expense actually suffered
viz. the compensation for prolongation caused other than by variations
is based on the actual additional cost incurred by the contractor.
* Relevance of tender - The tender allowance has limited relevance
for the evaluation of prolongation and disruption caused by breach
of contract or any other cause that requires the evaluation of additional
costs, though the tender allowance may be relevant as a base line
for the evaluation of prolongation and disruption caused by variations.
* Period of evaluation of compensation - Once it is established
that compensation for prolongation is due, the evaluation of the
sum due is made by reference to the period when the effect of the
Employer Risk Event was felt, not by reference to the extended period
at the end of the contract.
* Global claims - The practice of contractors making composite
or global claims without substantiating cause and effect is strongly
discouraged by the Protocol. o Disruption - (as distinct from delay)
is disturbance, hindrance or interruption to a contractor's normal
working methods, resulting in lower efficiency. If caused by the
employer, it may be open to compensation either under the contract
or as a breach of contract.
Reproduced with permission from Construction Industry
Law Letter, December 2001/January 2002, edited by Tony Francis (http://www.informalaw.com)
|