Society of Construction Law

Article in Electrical Times, December 2002

VALUING DELAY AND DISRUPTION

by John Russell FCIOB ACIArb

The Society of Construction Law has produced its final version of the “Delay and Disruption Protocol”. The object is to provide guidance to those who submit or respond to applications for extension of time and additional costs. The intention is to “provide a means by which the parties can resolve these matters and avoid unnecessary disputes”. Whilst it has no formal status, the protocol will inevitably to be used as a source of reference, initially on larger
projects. So what are the key recommendations?

Programme and records
A key essential is the early agreement of a programme, showing planned approach and sequences. This serves both as a management tool for progressing the works, and a baseline for recording and agreeing effects of delays and variations. As to site records, the precise format and frequency should be agreed between the parties at the outset.
Sorting out problems at the time The partiers are encouraged to identify and resolve problems at the time, together with extension of the period and agreement of additional costs. This approach should reduce end of job disputes.

Programme float
General float in the programme is there for the benefit of the project , rather than “owned by the sub-contractor”. However, the protocol suggests that specific contingency allowances may still be retained for the benefit of the sub- contractor, providing they are clearly shown and described on the programme. Where the parties have agreed at the outset to attempt an “early finish” or “target” programme, the protocol suggests that delay which eats into this “end
float” may entitle the sub-contractor to financial compensation, although no extension is required.

Concurrent delay
Where two causes of delay run side by side, one which is compensable and one is which culpable (ie the sub-contractor’s own fault), this should not reduce entitlement to extension of time. However, financial compensation is only applicable where the costs can be clearlyshown as flowing from the compensable delay.

Mitigation
The protocol recognises the common law duty of the sub-contractor to mitigate the effects of delays and costs. However, this duty should not involve the use of “special measures” eg extra labour and weekend working). In other words, mitigation should not involve significant additional costs.

Variations
The effects of variations, both in time and money, are best agreed up front, including any alterations to the programme. Where the character or conditions of the varied works differs from that set out within the original documents, then most existing contracts provide for revised rates to be agreed.

Prolongation costs
Prolongation costs , where financial entitlement is established, should be based on actual costs incurred at the time of the delay, rather than the “tail end” over-run. Use of tender allowances as a basis is discouraged.

Global claims
Rolled up “global” claims are strongly discouraged. Maintenance of good site records should enable the claimant to evaluate additional costs and attribute them to individual events under the sub-contract ie “cause and effect”).

Acceleration
Unless the contract contains special provisions, the special measures and costs of acceleration are best agreed in advance. The protocol advises against the common practice of claiming “acceleration” costs after the event, often referred to as “constructive” acceleration.

Disruption
This is described as “disturbance, hindrance or interruption to normal working methods”. Good records and labour allocation sheets are absolutely essential. One approach is to compare productivity on a “good” area with that on disrupted areas. In some cases, it may be permissible to use a previous project as a baseline. Mere percentage assessments are discouraged. However, acknowledgement is given to the possible use of published research (eg CIOB etc).

Head office overheads
The protocol recommends that “dedicated overheads” (eg time spent by head office managers and staff) should be recorded to individual projects as a matter of routine, so that the claimed costs can be established and verified. As to the more general overheads (eg rent and rates etc) it is necessary to prove that a loss took place due to the prolongation, and that this could not be recovered elsewhere. If a formula is used, then credit should be made for additional recovery via variations.

Conclusion
One cannot quarrel with the commendable aims of the protocol. The emphasis on programming and early identification and management of problems is very similar to the widely used NEC contract. However, if the protocol recommendations are diligently followed, there will be a need for additional staff on site to handle the demanding regime of notices, records and forecasts. In particular, there is a need for more planners. The question is whether smaller projects can accommodate the extra costs required to operate the procedures.

Reproduced with permission from Electrical Times (http://www.jrconsultant.co.uk)